Hi,
How to add the delays with Predecessors like 6SS+10days in WinGanttView.
I showed the example in Print Screen, which is created in MS Project.
I`m not sure that I understand your scenario, but maybe you could add delay if you change the start date or drag the task to new date. As far as I know you could not use Predecessors with mentioned format and add a delay.
Please let me know if you think that I misunderstood your scenario or if you have any questions.
See the attachment of the below image, in that see 9th Row Predeccssor says that "8SS+7 days" means that 8 th row of starting Date and add the 7 days then the 9th row of starting date will appear automatically. for example 8th row Date "2 aug 2011" , 9 th row Predecessor is 8SS+7 days then 9th row Starting Date "9 aug 2011", it fill automatically.
If not able to add the delay then Is there any other option to add new column or any other existing column to have a delays in days or integer values so we can add that days with mentioned previous predecessors date value?