Your Privacy Matters: We use our own and third-party cookies to improve your experience on our website. By continuing to use the website we understand that you accept their use. Cookie Policy
185
Manual PercentComplete
posted

Hi,

 

How can I set the PercentComplete value of SummaryTasks manually?

Take for instance 2 Tasks, task A with duration of 1 day and task B with duration of 10 days.

Task A is 100% complete, Task B 0%. It makes no sense saying that the job is half done (50%).

Only 1 day out of 11 is complete. The summary should be 9% complete.

 

Thank you

 

  • 12480
    Offline posted

    Hello,

    After some research, this has been determined to be a new product idea.  I have sent your product idea directly to our product management team.  Our product team chooses new product ideas for development based on popular feedback from our customer base. Infragistics continues to monitor application development for all of our products, so as trends appear in requested features, we can plan accordingly.

    We value your input, and our philosophy is to enhance our toolset based on customer feedback.  If your feature is chosen for development, you will be notified at that time.  Your reference number for this product idea is PI12060104.

    If you would like to follow up on your product idea at a later point, you may contact Developer Support management via email.  Please include the reference number of your product idea in the subject and body of your email message.  You can reach Developer Support management through the following email address:  dsmanager@infragistics.com

    Thank you for your request.