Your Privacy Matters: We use our own and third-party cookies to improve your experience on our website. By continuing to use the website we understand that you accept their use. Cookie Policy
40
Show exact timeline length having a Months/Weeks primary interval
posted

I'm using a WinGanttView with a configurable primary interval of days, weeks, and months.  When viewing the timeline with a Months primary interval and if a task's start date falls in the middle of a month, the timeline bar displays as if the task started at the beginning of that particular month.  Is this the expected behavior?  If not, how can I configure it to display the exact bar length according to the duration, just how it is in MS Project.  The same case is also observed when using Weeks primary interval.

We are using NetAdvantage for Windows Forms version 10.3

Please see screenshots below:

Primary Interval: Months 

Notice that 2 tasks have only 62 days duration but their timeline bars are equal to the length of tasks with 92 days duration:

 

Primary Interval: Weeks

Notice that the timeline bars started on Sept. 26 even though the tasks' start date is still on Oct. 1.

Thanks!

Parents Reply Children