Your Privacy Matters: We use our own and third-party cookies to improve your experience on our website. By continuing to use the website we understand that you accept their use. Cookie Policy
600
adding non working days
posted

hi,

Can I add more non workingdays to the gantt view.

thanks

 

Parents
No Data
Reply
  • 69832
    Verified Answer
    Offline posted

    Currently you can only change the workday status for a day of the week, i.e., not individual days. NA 2010.2 will contain support for designation of non-working days/hours on a per-day basis.

    You can make a day of the week a non-working day by setting the IsWorkDay property to false for that day of the week. You can access the day of week objects from the UltraCalendarInfo.DaysOfWeek collection.

Children
No Data